Facilities Development
Buildings File, 1961-1977

This segment of the Buildings File of the Washington State University Facilities Planning office was transferred to the Washington State University Libraries in 1984 (UA84-21). The records were processed in July 1984 by Ann Klavano. The descriptions were expanded in Summer 2000 by Brenda Jackson.

Number of containers: 5
Linear feet of shelf space: 5
Number of folders: 181

HISTORY

A University Architect has served as the construction officer at Washington State University since 1911. The modern form of the office dates from 1947 when it became a full-time, staffed administrative department. In 1967 the office was renamed as Facilities Planning, and later as Facilities Development and still later as Capital Planning. It is responsible for the major construction projects of the university.

ARRANGEMENT AND DESCRIPTION

Records of Facilities Planning are arranged according to the building number system that identifies most structures owned by Washington State University. The archival arrangement follows office practice without variance.

Locating records relevant to a specific project normally requires having the building number available.

The records consist of correspondence, reports, bidding records and other document related to the work of architects and construction contractors.

CONTAINER LIST

Box Folder   Description
Hollingbery Field House - Bldg. 9
11   Dedicatory Plaque, 1963
2   General Correspondence, 1966-1974
Proposed Psychology Building - Bldg. 74
3   Correspondence, 1966
Heald Hall - 5th Floor Addition - Bldg. 82
4   Budget
5   General Correspondence, 1966-1967
6   General Correspondence, 1968-1979
7   Warren, Little & Lund, Inc., Correspondence, 1967-1969
8   Warren, Little & Lund, Contract & C.O.s
9   Decker, Kolb, Stansfield, Architects, Corres., 1967-1969
10   Decker, Kolb, Stansfield, Architects, Corres., 1966-7
11   Decker, Kolb, Stansfield, Architects, Contract & C.O.s
12   Decker, Kolb & Stansfield, Construction Reports
13   Concrete Testing
14   Kehne-Crabtree Electric Co., Correspondence, 1967-1968
15   Kehne-Crabtree Electric Co., Contract & C.O.s
16   C&S Builders, Inc., Correspondence, 1967-1968
17   C&S Builders, Inc., Contract & C.O.s
18   N.S.F. (National Science Foundation) & N.I.H (National Institutes of Health) Correspondence, 1967
19   N.I.H. Grant Application
20   N.S.F. Proposal
21   Rejected Bids - General, 1967
22   Rejected Bids - Mechanical, 1967
23   Rejected Bids - Electrical, 1967
24   Projected Equipment Expenditures
McCluskey Addition - Bldg. 85
25   Budget
26   General Correspondence, 1973-1974
27   Diary Inspection Report, 1973
28   Victor L. Wulff, Arch., Correspondence, 1973-1974
29   Victor L. Wulff, Arch., Contract, Estimates, C.O.s
30   Space Builders, General Correspondence, 1973-1974
31   Space Builders, Contract, Payments, C.O.s
32   Rejected Bids
Design Disciplines Bldg., Phase I (Fine Arts)- Bldg. 97
33   Parking Structure Budget
34   Building Program
35   Budget
36   HEFA Correspondence, 1968-1971
37   General Correspondence, 1966-July 1968
38   General Correspondence, July 1968-December 1968
39   General Correspondence, January 1969 - December 1970
40   General Correspondence, January 1971 - 1974
41   General Correspondence, Parking Correspondence
42   Parking Study, Tippetts, Abbett, McCarthy, Stratton
43   Naramore, Bain, Brady & Johanson, Corres., 1966-1967
244   Naramore, Bain, Brady & Johanson, Corres., 1-68-6/68
45   Naramore, Bain, Brady & Johanson, Corres., 7/68 - 12/68
46   Naramore, Bain, Brady & Johanson, Corres., 1969
47   Naramore, Bain, Brady & Johanson, Corres., 1970
48   Naramore, Bain, Brady & Johanson, Corres., 1/71 - 6/71
49   Naramore, Bain, Brady & Johanson, Corres., 7/71 - 4/77
50   Naramore, Bain, Brady & Johanson, Contract & C.O.s
51   Naramore, Bain, Brady & Johanson, Site Visit Reports
52   Weekly Progress Reports & Employee Interview Reports
53   Naramore, Bain, Brady, et al., Conference Notes
54   Bouillon, Christofferson & Schairer, Cons. Eng., Report of Site Visit
55   Max J. Kuney Co., Contract & C.O.s
56   Max J. Kuney Co., Correspondence, 1968-1979
57   Shannon & Wilson, Inc., Soils Investigations
58   Shannon & Wilson, Inc., Correspondence, 1967
59   Warren, Little & Lund, Inc., Contract & C.O.s
60   Warren, Little & Lund, Inc., Corres., 1968-1971
61   Babbitt Electric & Refrigeration, Corres., 1968-1972
62   Babbitt Electri Co., Contract & C.O.s
63   Babbitt Electric Co., Claim
64   Hardware Schedule
65   Pittsburgh Testing Labs, Concrete Testing
66   Keying Schedule
67   Furnishings, Correspondence, 1967
68   Rejected Bids, Mechanical
69   Rejected Bids, General
70   Rejected Bids, Electrical
71   Awards Brochure
Controlled Environment Laboratories, Phase I - Bldg. 114
372   Budget
73   General Correspondence, 1970-1974
74   Diary Inspection Reports
75   Carlson & James, Architects, Correspondence, 1970-72
76   Carlson & James, Contract, Payments & C.O.s
77   C&S Builders, Inc., Correspondence, 1970-72
78   C&S Builders, Inc., Contract, Payments, C.O.s
79   Elling Halvorson, Inc., Correspondence, 1970-1971
80   Elling Halvorson, Inc., Contract, Payments, C.O.s
81   Sub-Grade Investigation
82   Rejected Bids - General
83   Rejected Bids
84   Rejected Bids
Controlled Environment Laboratories, Phase II - Bldg. 114
85   Budget
86   General Correspondence, 1970
87   Carlson & James, Architects, Correspondence, 1970
Veterinary Barn Remodel - Bldg. 141G
88   Budget
89   Diary Inspection Reports
90   General Correspondence, 1973
91   Victor L. Wulff, Architect., Corres., 1973-1974
92   Victor L. Wulff, Arch., Contract, Payments, C.O.s
93   Gil Bauer Construction Co., Correspondence, 1974
94   Gil Bauer Construction Co., Contract, Payments, C.O.s
95   Rejected Bids
KWSC Transmitter Tower - Bldg. 403A
96   Budget
97   Specifications
98   General Correspondence, 1961-1968
99   Correspondence, 1969-1974
100   Midwest Tower Inc., Correspondence, 1968-1969
101   Midwest Tower, Inc., Contract & C.O.s
102   Pittsburgh Testing Labs., Contract & C.O.s
103   Vern W. Johnson & Sons, Correspondence, 1968-1969
104   Vern W. Johnson & Sons, Contract & Change Orders
105   Rejected Bids
106   Rejected Bids, Contractors
Turnkey Student Housing - Bldg. 675
107   Budget
108   Program
109   HUD Correspondence, 1971-1973
110   General Correspondence, 1969-1970
111   General Correspondence, 1971-1974
112   Daily Inspection Reports, 1970-71
113   Heating & Close-Out Problems, 1972-77
114   United Homes Corp., Correspondence, 1970-73
115   Olson-Richert-Bignold, Correspondence, 1970-1971
4116   Olson-Richert-Bignold, Contract, Payments, C.O.s
117   United Homes Corp., Contract, Payments, C.O.s
118   United Homes Corp., Proposal
119   United Homes Corp., Affirmative Action Reports
120   Pittsburgh Testing Labs., Concrete Testing
121   Furnishings, Correspondence, 1970-74
122   Neill Furniture Stores, Inc., Correspondence, 1971-72
123   Neill Furniture Stores, Contract, Estimates, C.O.s
124   Richard D. Rosell, Int. Design, Contract, Payments, C.O.s
125   Rejected Bids
126   Rejected Bids, Furniture
127   Rejected Bids, Furnishings
Speech Building (Daggy Hall)- Bldg. 803
128   Budget
129   General Correspondence, 3/70 - 12/71
130   General Correspondence, 1/72 - 8/77
131   Diary Inspection Reports
132   Fred Bassetti & Co., Correspondence, 2/70 - 12/71
133   Fred Bassetti & Co., Correspondence, 1/72 - 6/72
134   Fred Bassetti & Co., Correspondence, 7/72 - 12/72
135   Fred Bassetti & Co., Correspondence, 1/73 - 6/75
136   Fred Bassetti & Co., Site Visit & Monthly Construc. Mtg.
137   Fred Bassetti & Co., Contract, Payments, C.O.s
138   Warren, Little & Lund, Correspondence, 1971-1973
139   Warren, Little & Lund, Contract, Payments, C.O.s
140   Warren, Little & Lund, Affirmative Action Reports
141   Halvorson-Berg, Correspondence, 1971-1974
142   Halvorson-Berg, Contract, Payments, C.O.s
143   Halvorson-Berg, Affirmative Action Reports
144   Electric Smith & Rod's Electric, Corres., 1971-1973
145   Electric Smith & Rod's Electric, Affirmative Action Repts.
146   Electric Smith & Rod's Electric, Contract, Payments, C.O.s
147   Stagecraft Industries, Correspondence, 1971-1975
148   Stagecraft Industries, Contract, Payments, C.O.s
149   Stagecraft Industries, Affirmative Action Reports
150   Pittsburgh Testing Labs., Concrete Testing
151   Pittsburgh Testing Labs., Steel, Mortar, Grout Testing
152   Hardware Schedule
153   Geolabs, Inc., Inspections Reports & Add'l Recommendations
154   Rejected Bids, General Construction
155   Rejected Bids, Electrical Construction
156   Rejected Bids, Mechanical Construction
157   Rejected Bids, Stage Equipment
158   Rejected Bids, General
159   Rejected Bids, Mechanical
160   Rejected Bids, Electrical
Arts Hall Remodel (Murrow East)- Bldg. 33
5161   Skyline Construction Co., Contract, Payments, C.O.s
162   Diary - Inspection Reports
163   Skyline Construction Co., Correspondence, 1971-1972
Expo '74 - Waterworld Pavillion
164   Correspondence, 1974
165   Lydig Construction, Inc., Correspondence, 1974
166   Lydig Construction, Inc., Contract & Payments
167   AAA Construction Co., Contract, Payments, C.O.s
Jogging Track
168   General Construction, 1982-1983
KWSU Translator Tower - Lind
169   Budget
170   General Correspondence, 1967-1969
171   Fort Worth Tower Co., Correspondence, 1969-70
172   Fort Worth Tower Co., Contract, Payments, C.O.s
173   Rejected Bids
Pavement Test Track Rings
174   Budget
175   General Correspondence, 1967-1973
176   United Paving Co., Inc., Correspondence, 1967-1969
177   United Paving Co., Inc., Contract & C.O.s
Paths and Steps (Small Jobs)
178   Correspondence, 1968-1974
Walks and Steps, Gym Area
179   Sceva Construction Co., Correspondence, 1968
180   Sceva Construction Co., Contract & C.O.s
181   Rejected Bids